Blendon Township planning commissioners voted 3-3 on New York-based Key Capture Energy’s proposed 100-megawatt battery energy storage facility on 88th Avenue near Polk Street in Ottawa County.
The project utilizes shipping container-sized lithium-type batteries to draw power from the electrical grid during non-peak hours, releasing the stored energy back into the grid during times of high-demand.
Director of Public Affairs and Community Engagement for Key Capture Chris Linsmayer has stated that, should commissioners and the company fail to reach an agreement, the company would consider bypassing township approval through the Michigan Public Service Commission under the state’s Public Act 233.
“You know, we’ve been working with the town for over a year on this. We’re really hopeful to get a positive outcome and we’ve adjusted the project several times at the request of the planning commission and the town, so hopefully we’re able to be successful and then build a project to those local parameters.”
The project has received significant pushback from residents over noise, fire, and environmental concerns.
Commissioners will consider voting again on December 7th.