U.S. Secretary of Energy Chris Wright used emergency powers to keep the J.H. Campbell power plant open for another three months.
The coal-burning plant, located in West Olive and owned by Consumers Energy, was scheduled for decommissioning in May 2025, but the Trump administration ordered it remain open using authority typically reserved for periods of power-demand related emergencies.
State regulators approved the closure in 2022, assuring grid reliability. Consumers Energy projected $600 million in savings for ratepayers. Since the first emergency order, Consumers reports more than $300 million in costs to customers across the Midwest.
Critics like Michigan Attorney General Dana Nessel believe the orders are under the pretense of a fabricated energy emergency, stating, “In September, a federal court ruled DOE’s first Campbell plant order was entirely illegal, and this seventh order makes no further effort to comply with the law.”
AG Nessel also argues that because the underlying DOE orders are unlawful, recovering costs from ratepayers is also unlawful.
The latest order keeps the plant operating until February 12th. Consumers Energy says it will comply with that order.
For a weekly dose of news right to your inbox, sign up for the WGVU newsletter.