Report: Cost of upgrading Flint's water plant rises to $108M

Picture of Flint water tower
flickr.com

A consultant says the cost of upgrading Flint's water treatment plant is estimated at $108 million, up slightly from an earlier estimate.

The Flint Journal says the recent report by engineering and construction company CDM Smith includes $37 million for the construction of two, 21-million gallon water storage tanks and more than $34 million for pump and transfer station upgrades.

A December draft report put the cost at $105 million. Flint will treat Lake Huron water from a new pipeline.

The plant improperly treated water from the Flint River in 2014-2015, leading to the city's crisis with lead-tainted water.

The report estimates work on the plant can be completed in 2019-2020.

The state Department of Environmental Quality must agree to the final version of the consultant's report.